1803 Electric Cooperative, Inc. is a generation and transmission cooperative founded in 2019. 1803 supplies wholesale power service to six Louisiana member distribution cooperatives.1 Integrated resource planning is the process 1803 uses to develop a long-range plan for meeting its members’ future electricity needs reliably and at the lowest reasonable cost.
The Louisiana Public Service Commission established uniform integrated resource planning rules for the electric utilities it regulates in General Order No. 08-28-2024 (R-36262) (Corrected), dated August 28, 2024. 1803 initiated its current integrated resource planning cycle by correspondence filed with the Commission on July 29, 2026, in Docket No. I-38052.
As the power supply cooperative for its full-requirements members, 1803’s integrated resource planning process also satisfies the integrated resource planning requirements of each of its member cooperatives.
Schedule of Events
The following schedule was filed with the Commission on July 29, 2026 as Exhibit A to 1803’s Request to Initiate Integrated Resource Planning Process. Dates are subject to change. Any revisions will be posted on this page.
| Event | Description | Date |
|---|---|---|
| 1 | 1803 submits its request to initiate the IRP process, with dates specified for schedule of events, and NDA | July 29, 2026 |
| 2 | 1803 files data assumptions to be used in the IRP and a description of studies to be performed | August 28, 2026 |
| 3 | First stakeholder meeting | September 29, 2026 |
| 4 | Stakeholders written comments due | December 4, 2026 |
| 5 | Draft IRP Report published | July 29, 2027 |
| 6 | Second stakeholder meeting | August 27, 2027 |
| 7 | Stakeholders written comments on draft IRP Report due | October 29, 2027 |
| 8 | LPSC Staff written comments on draft IRP Report due | December 3, 2027 |
| 9 | Final IRP Report published | February 25, 2028 |
| 10 | Stakeholders list of disputed issues and alternative recommendations due | April 25, 2028 |
| 11 | Staff submits recommendation to Commission including whether or not a proceeding is necessary for resolution of issues | May 25, 2028 |
| 12 | Commission Order acknowledging IRP or setting procedural schedule for disputed issues | August 2028 B&E Session (if no July) |